28. 3 men can complete a piece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?
A.6 Days B.4 Days
C.2 Days D.8 Days
Answer:
Work done by 3 men in 2 days = (1/6x 2 )=1/3.
Remaining work = (1 – 1/3)= 2/3
Now 3 men's 1 day's work =1/6
1 man's 1 day's work = 1/18
6 men's 1 day's work = (6 x 1/18=1/3
Now, 1/3 work is done by them in 1 day.
:. 2/3 work is done by them in (3 x2/3)= 2 days.