65.
|
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :
|
|
|
4 days
|
|
6 days
|
|
|
8 days
|
|
12 days
|
|
Answer: Option C
Explanation:
(A + B + C)'s 1 day's work =
|
1
|
;
|
6
|
(A + B)'s 1 day's work =
|
1
|
;
|
8
|
(B + C)'s 1 day's work =
|
1
|
.
|
12
|
So, A and C together will do the work in 8 days.