67.
|
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
|
|
|
Answer: Option C
Explanation:
(B + C)'s 1 day's work =
|
|
1
|
+
|
1
|
|
=
|
7
|
.
|
9
|
12
|
36
|
Work done by B and C in 3 days =
|
|
7
|
x 3
|
|
=
|
7
|
.
|
36
|
12
|
Remaining work =
|
|
1 -
|
7
|
|
=
|
5
|
.
|
12
|
12
|
Now,
|
1
|
work is done by A in 1 day.
|
24
|
So,
|
5
|
work is done by A in
|
|
24 x
|
5
|
|
= 10 days.
|
12
|
12
|